Building Project Site: The Wellspring Church Centre - Watford Community Church

August/September 2010

During August and September work has progressed internally throughout the building-
  • The lift has been installed and commissioned
  • The main stair has been erected together with the feature balustrade
  • Internal partitioning has been completed and doors hung
  • Decorations, ceilings and laying of floor coverings are in progress
  • Fitting out of toilets is in progress
  • Commissioning and testing of services installation now under way
Externally work has also progressed with perimeter fence erected and paving in progress.

As we now move towards occupation, work continues on the Auditorium ceiling together with installation of audio systems. During this period all the finishing trades will progress through the building and testing of the various building systems will be completed.